Nasara Manufacturing Plc has three direct labour employees that work 40 hours each a ...

Nasara Manufacturing Plc has three direct labour employees that work 40 hours each a week for 50 weeks a year. Factory overhead costs of N60,000 is distributed on the basis of direct labour hours.
Compute the overhead rate?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
  • A N12 per hour
  • B N16 per hour
  • C N10 per hour
  • D N15 per hour
Correct Answer: Option C
Explanation: