Use the information below to answer question . Prime cost..................N12 ...

Use the information below to answer question .
Prime cost..................N12 100
lighting....................N10 000
Heating.....................N15 000
Factory overhead............?
The production department share of factory overhead is 1/4 and 1/2 of lighting and heating respectively.
The factory overhead is?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
  • A N5050
  • B N7250
  • C N2750
  • D N5500
Correct Answer: Option D
Explanation:

Share question on: