Given: Stock at start: Raw materials................N57 ...

Given:
Stock at start:
Raw materials................N57 000
Work-in-progress.............N42 000
Finished goods...............N71 000
Purchase of raw materials amount to N81 000, direct labour is N38 000 and factory overhead N29 000.
Calculate the prime cost?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
  • A N176 000
  • B N170 000
  • C N167 000
  • D N156 000
Correct Answer: Option A
Explanation: