A contract terminated by the occurence of an event which makes performance impossible is discharged by?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
Correct Answer: Option C
Explanation:
frustration of contract; is the Legal termination of a contract due to unforeseen circumstances that (1) prevent achievement of its objectives, (2) render its performance illegal, or (3) make it practically impossible to execute.