Question 1:
Given: N
Direct material - 10 000
Direct labour - 5000
Direct expenses - 2000
Factory overhead - 4000
What is the prime cost?
View Answer & ExplanationDirect material - 10 000
Direct labour - 5000
Direct expenses - 2000
Factory overhead - 4000
What is the prime cost?
Question 2:
Depreciation on a particular piece of machinery was N2,700 during the fifth year of its service life and N4,050 during the sixth year. The logical explanation for this is that?
View Answer & ExplanationQuestion 3:
Lawal and co makes blocks and sell to builders.
In computing prime cost, which of the following costs would be considered appropriate?
View Answer & ExplanationIn computing prime cost, which of the following costs would be considered appropriate?
Question 4:
Given:
Depreciation of plant and machinery N1,600
Factory rent N650
Indirect wages N695
General indirect expenses N726
lubricants N1235
Carriage inwards N829
Factory power N350
Bank charges N612
Carriage outwards N2,900
Determine the total factory overhead cost?
View Answer & ExplanationDepreciation of plant and machinery N1,600
Factory rent N650
Indirect wages N695
General indirect expenses N726
lubricants N1235
Carriage inwards N829
Factory power N350
Bank charges N612
Carriage outwards N2,900
Determine the total factory overhead cost?
Question 5:
Given:
Direct material N2,500
Direct labour N5,000
Direct expenses N1,000
Overhead expenses N1,500
From the data above, compute the prime cost?
View Answer & ExplanationDirect material N2,500
Direct labour N5,000
Direct expenses N1,000
Overhead expenses N1,500
From the data above, compute the prime cost?