A bricklayer charges #1,500 per day for himself and #500 per day for his assistant. If a two bedroom flat was built for #95,000 and the bricklayer worked 10 days more than his assistant, how much did the assistant receive?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
Correct Answer: Option A
Explanation:
Let the number of days worked by the assistant = t
\(\therefore\) The bricklayer worked (t + 10) days.
1500(t + 10) + 500(t) = N 95,000
1500t + 15,000 + 500t = N 95,000
2000t = N 95,000 - N 15,000
2000t = N 80,000
t = 40 days
\(\therefore\) The assistant worked for 40 days and received N (500 x 40)
= N 20,000