The time taken to do a piece of work is inversely proportional to the number of men ...

The time taken to do a piece of work is inversely proportional to the number of men employed. If it takes 30 men to do a piece of work in 6 days, how many men are required to do the work in 4 days?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
  • A 20
  • B 35
  • C 45
  • D 60
Correct Answer: Option C
Explanation:
t = time taken and N = number of men
t ∝ 1/N
t = K/N
K = Nt
K = 30 * 6
K = 180
∴t = 180/N
4 = 180/N
4N = 180
N = 180/4
45 men