In CIF contracts, risk passes at the time of shipment but the property does not pass ...

In CIF contracts, risk passes at the time of shipment but the property does not pass until?
Take Free Practice Test On 2026 JAMB UTME, Post UTME, WAEC SSCE, GCE, NECO SSCE
  • A There is physical transfer of goods
  • B The shipping manifest are signed
  • C The shipping documents are transferred
  • D The goods on board are delivered
Correct Answer: Option B
Explanation: